Skip to content
New Pumping Station North America

Ontario Cooling Tower Chemical Skid

A food plant replaced drum-and-metering-pipe dosing with an AF-D skid; biocide and acid feed now track conductivity within two percent, and the water treatment audit closed clean.

Chat With Lena
01 / Background

Project Background

The plant runs two cooling towers with a combined recirculation of 900 cubic metres per hour. Chemicals were hand-dosed from drums with a metering pipe, which the corporate audit flagged twice.

Legionella control logging was also manual, which failed the insurance checklist.

Product
Dosing Pumps
Fluids
Chemicals
Applications
Chemical Dosing
Ontario Cooling Tower Chemical Skid installation photo
02 / Requirement

The Requirement

Biocide at 4 litres per hour and sulfuric acid at 12 litres per hour, both modulated by tower conductivity, with local logging retained for 12 months.

Everything had to fit in the existing 2-by-1.5 metre chemical room next to the towers.

03 / Solution

Pumps And Configuration Supplied

One AF-D dosing skid with two metering pumps (AF-D-100 for acid in PVDF, AF-D-030 for biocide), a 200-litre day tank each, and a compact controller that logs every dose to an SD card and the plant network.

The skid was wet-tested with water at our factory and the client witnessed the calibration run over video.

Dosing Pumps

Dosing Pumps

AF-D-100 PVDF (acid) and AF-D-030 PVDF (biocide), 4-20 mA control from conductivity

Day Tanks

Day Tanks

2 x 200 L HDPE tanks with level switches and drip containment

Controller And Logging

Conductivity-linked controller, SD card plus Modbus TCP to the plant network, 12-month log retention

04 / Photos

Project Photos

The finished skid, the pump manifold detail, and the controller cabinet during the witness test.

Ontario Cooling Tower Chemical Skid project photo
Ontario Cooling Tower Chemical Skid project photo
Ontario Cooling Tower Chemical Skid project photo
05 / Result

Result After Commissioning

Dose tracking holds within two percent of the conductivity setpoint, and the corporate water treatment audit closed with no findings.

Chemical consumption fell 11 percent because dosing now stops exactly at target instead of overshooting.

Related Products

Series Used In This Project

Series

Dosing Pumps

Open Product Page
Next Step

Quote A Similar Pumping Station

Send the duty point and site details, and our sales engineer returns a selection and a quotation.

Chat With Lena